How to sell to Maldives resorts
A supplier's guide to how resort projects run in the Maldives, how to read the public filings, and when to make contact.
1. The market in numbers
Every Maldives resort is its own island: one resort, one island, one leaseholder. Almost everything is imported and shipped by sea, so each resort is a separate logistics project and a separate buyer.
Our register lists 178 resorts with 22,336 rooms, and 162 more islands and lagoon plots leased for resort development. Statistics by atoll · Map
2. How a resort project runs
The Ministry of Tourism leases an island or lagoon for resort development. The developer then needs an approved master plan, an environmental assessment, and a construction permit before building, and an operating licence before opening. The ministry's Development Handbook for Tourist Resorts ↗ sets out the steps, including construction periods, extensions and duty exemptions.
We follow each named project through five stages:
26 named projects by stage
Target openings by year
Stages are our reading of public announcements and environmental filings, not official status. Opening years are developers' own targets. See every project
3. What is bought at each stage
| Stage | Public signals | Typically bought |
|---|---|---|
| Lease / development announcement | Lease or development announcement; Owner/developer identified; Operator signing | Feasibility, surveys, design and engineering services |
| EIA / planning / design | EIA report or public consultation; Coastal works proposal; Design appointment or mock-up plan | Marine and coastal works, design consultants, mock-up suppliers |
| Contractor appointment / construction | Main contractor or package award; Mobilisation; Civil/marine works start | Structures, prefabrication, utilities, energy, water and waste plant |
| Interiors / FF&E specification and procurement | Interior designer appointed; Mock-up room; Fit-out package or room-furniture programme | Furniture, fixtures, lighting, kitchens, laundry, AV and IT |
| Pre-opening / OS&E | Pre-opening GM or purchasing team appointed; Recruitment ramp-up; Opening date reaffirmed | Operating supplies, uniforms, boats, water sports, software |
| Operating resort / recurring purchasing | Operating licence or current operation verified; Purchasing/engineering vacancy or appointment; Replacement, service or sustainability initiative | Replacement, maintenance, consumables, efficiency upgrades |
| Renovation / conversion / expansion | New EIA for an existing resort; Closure/refurbishment announcement; Brand conversion; Additional villas or infrastructure | Everything above, on a shorter timetable |
Who decides at each stage, what to ask and the official supplier registration routes are on the buyer routes page.
4. Reading the environmental filings
Before a resort dredges, reclaims, builds water villas or replaces major plant, an environmental document is filed with the authority, and the index of those documents is public. A filing shows intent and scope. It is not an approval, and it does not say who won the work.
| Type | What it means for a supplier | In our index |
|---|---|---|
| EIA report | Environmental Impact Assessment. Filed before works that can significantly affect the environment: a new resort, reclamation, dredging, a harbour, water villas. The clearest early sign of a new build. | 1,632 |
| EIA addendum | A change or extension to a project that already has an assessment. Typical for an existing resort adding villas, extending a jetty or changing its design. | 368 |
| EMP | Environmental Management Plan. Used for smaller, more routine works such as replacing a desalination plant, a fuel store or a sewage treatment plant. | 160 |
| ESMP | Environmental and Social Management Plan. Mostly public and donor-funded infrastructure, rarely resorts. | 33 |
| Environmental record | Other entries in the index that do not state their type. | 26 |
| ESIA report | Environmental and Social Impact Assessment. The donor-standard version of an EIA, mostly for public infrastructure. | 23 |
Open the projects tracker for plain-English summaries of resort filings, or search all 2,242 filings.
5. Tax and import duty
- Tourism GST is 17% since 1 July 2025 (previously 16%). It applies to what resorts sell to guests. Source ↗
- Import duty exemptions can be requested for machinery, capital equipment and construction materials on approved tourism development projects. The developer applies, not the supplier, so ask early whether your goods will come in under the project's exemption. oneGov guideline ↗
- A government policy also makes materials for resort development in Haa Alifu, Haa Dhaalu, Shaviyani, Thaa, Laamu and Addu eligible for exemption, to draw investment to atolls with less tourism. Source ↗
General information, not tax advice. Rules change; confirm with Maldives Customs, MIRA or a local adviser.
6. Trade shows
| Show | Last edition | Next |
|---|---|---|
| FHAM · Food & Hospitality Asia Maldives | 7–9 September 2026, Hulhumalé ↗ | 2027 dates not announced when checked |
| Hotel Asia · International Food & Hotel Suppliers Exhibition | 28–30 September 2026, Hulhumalé ↗ | 2027 dates not announced when checked |
7. Checklist before you make contact
- Match your product to the stage. Marine contractors need to be in at the EIA; furniture suppliers when the interior designer is appointed; operating supplies in pre-opening.
- Find out who buys. The owner directly, the main contractor, a procurement agent, or the hotel brand's approved-vendor list. It differs per project.
- Check the entity. The brand on the announcement is usually the operator, not the owner. The leaseholder or developer pays for the build.
- Read the filing yourself. Each record links to the source document. Check the scope and date before you quote it.
- Price in the logistics. Sea freight to Malé, transfer to the island and installation labour on site are part of every offer.